Vacuum degasser startup and shutdown operation steps

Vacuum degasser startup and shutdown operation steps

1. Add an appropriate amount of water to the vacuum separator; and turn on the power switch.

2. Press the start button of the main engine, press the start button of the vacuum pump after the main engine runs normally, adjust the pressure valve according to the regulations, and the degasser starts to work.

3 Press the stop button of the vacuum pump when it is turned off, and press the stop button of the host after the vacuum pump stops working.

4 Turn off the power; drain the water in the gas-water separator
Vacuum degasser

The drilling fluid vacuum degasser, usually installed after the drilling fluid vibrating screen, can effectively separate harmful gases in the drilling fluid mud, while maintaining the specific gravity of the mud, and protecting the sand pump and mud pump to improve the treatment of subsequent equipment Effect. The vacuum degasser can also function as a large agitator.

Welcome to send inquiry to us: sales@hlsolidscontrol.com if you want to know more about the degasser.

Prev: The working principle of the vacuum degasser Next: 32SB180J-2.2 electric spray pump
Product Center
Drilling Tools and Spare Parts
Solids Control Equipment
Mud Treatment System
Tank and Steel Structure
Hot Selling
Mission Pump Parts
Slurry Pump ( Vertical Sand Pump )
Sludge Vacuum Pump
Centrifugal Sand Pump